Here are the final numerical results for each section of the exam. You can use them to check your work if you do the exam for practice. If you have trouble with the problems, or don't get the answers shown here, stop by during office hours or make and appointment and we can go over them.
(a) Qa total = 600;
(b) Qp1 = 300; Qp2 = 100; 400 permits total;
(c) Qa total = 500;
(d) DWL = $20,000;
(e) P = $1,200;
(f) Firm 1 sells 100 permits to firm 2 for $120,000 of revenue.
(a) Number of visitors=6,300;
(b) A = 25.36, B = -0.00244;
(c) CS = $131,902;
(d) Value to non-visitors = $50,000;
(e) PV = $1.82 million.
(a) Value = $60 million; don't sell.
(a) Q = 250;
(b) $625 million;
(c) Q = 40;
(d) -$332 million;
(e) Neighborhood will vigorously oppose the project unless compensated approximately $332 million.
(a) The table is shown below:
Pd | R |
MEC |
P |
Q |
0 | 50 |
40 |
90 |
205 |
1 | 100 | 50 | 150 | 275 |
2 | 200 | 60 | 260 | 320 |
(b) With the backstop, the table becomes:
Pd |
R |
MEC |
P |
Q |
0 |
20 | 40 | 60 | 220 |
1 |
40 | 50 | 90 | 305 |
2 |
80 | 60 | 140 | 380 |
(c) Backstop production=105.
(a) MDC = $100;
(b) P = $150;
(c) The table without exploration:
Pd |
R |
MEC |
P |
Q |
0 |
100 | 50 | 150 | 175 |
1 |
200 | 50 | 250 | 175 |
(d) The table with exploration:
Pd |
R |
MEC |
P |
Q |
0 |
50 | 50 | 100 | 200 |
1 |
100 | 50 | 150 | 225 |
(e) Resource found via exploration = 75;
(f) Expected number of wells = 37.5.